The chilly weather has not stopped progress on the construction project! Steel erection continues on the new medical building and two-story ICU/Step Down. The floor slab for this addition will be poured soon, weather permitting. The steel erection on the new surgery addition has started and construction of the new surgery drop off and partial demo of three offices on the 1st floor of the existing medical building to support the new utility service will start in the next couple weeks. Storm lines and sanitary sewer installation, demolition of the remainder of the south parking lot, and pouring sidewalks and curbs will begin soon. The interior demolition on the existing administration support area is 90% complete and this will allow the connection to the new medical building steel. Also, recently there was a state 100% construction completion inspection which involved the new receiving dock, support areas, new server room and the new MRI/mobile Imaging trailer corridors. Thanks to everyone for their help with this.